- Team Info:
- Team name: Team Number 1
- Team mailing list: teamnumber1@mit.edu
- Team members, usernames, cell phone, google account name:
- Ani Mazumdar, AMAZUMDA, 949.241.2829
- Dan Schultz, DANIELT, 585.330.8938, mr.danielschultz
- Marcus Lopez, MARCUSL, 480.650.8782
- Martin McBrien, MMCBRIEN, 714.653.5886, martmcb
- Will Bosworth, BOSWORTH, 713.504.8802, wbosworth
- Advice from Prof. Culpepper:
- We will have to select the bushings for the carriage riding on the two rails
- We will have to choose the lead screw, the bearings for the end of the lead screw, and the lead screw nut
- We will have to design & manufacture the lead screw/carriage flecture
- We will have to choose the spindle shaft & bearings
- We will be given the housing for the spindle shaft
- We will have to make the decisions on the bolts/threads for the bolted joints
- The holes will be placed for us, we will tap them ourselves
- We will select the bolts & nuts for purchasing
- We must do the math to back up our decisions
- We will have to do most/all of the design & manufacturing for the drive train system
- Chain, gears, belt?
- Plan on this being a "huge time investment"
- We will be given the chuck/collet & tailstock
- We can assume for now that we will be given the crossfeed (though it might not be definite)
- Strongly recommended to water-jet pieces (frees up geometry constraints & production time)
- Team Schedule:
- The milestone is due on the date listed. The Gantt chart (to be made later) will show the overlapping work times.
- 2007.03.22 (R) - HTM for structures
- 2007.04.10 (T) - Drive train rough design & brainstorming
- 2007.04.12 (R) - Shafts done & bearings chosen...ready to be balanced by Prof & TAs
- 2007.04.19 (R) - Bolted joints math & selection
- 2007.04.20 (F) - Flecture design
- 2007.04.24 (T) - Final Drive Train Design
- 2007.04.26 (R) - Flecture prototype
- 2007.05.03 (R) - Final flecture
- Lead screw, lead screw nut, lead screw bearings selected
- 2007.05.11 (F) - Drive Train completed
- 2007.05.15 (T) - Report Draft1
- Future meetings will be held on Tuesdays after class (4pm) at Bexley Front Desk.
- This meeting on Google Docs: 2.72_TN1_2007.03.13_MeetingNotes